“Soil hasn't been tested yet. No basic or engineering done yet.”A buyer’s question
Your slab is designed to your soil. A geotechnical report classifies the site under AS 2870 (classes A, S, M, H, E and P), and the engineer designs the slab and footings to suit.
Engineering cannot be finalised without it, so get the soil test done early.
The steel brackets normally bolt down onto the finished slab. Cast in brackets are the exception, only where the loads demand them, and they are flagged at design stage so your concreter knows before the pour.
Always build the slab to the engineer's signed drawings.
Sources
- AS 2870 Residential slabs and footings
- Knowledge base
Brian Best, founder and builder, Shed Homes
Get the series by email
One short piece a week, straight from Brian. Unsubscribe any time.
General information only. Rules change, so check the current rule with your state regulator or council. Shed Homes supplies home kits and engineered documentation, and does not build.