Owner Builder Series, part 13 of 24. Engineered for Your Block

“Soil hasn't been tested yet. No basic or engineering done yet.”A buyer’s question

Your slab is designed to your soil. A geotechnical report classifies the site under AS 2870 (classes A, S, M, H, E and P), and the engineer designs the slab and footings to suit.

Engineering cannot be finalised without it, so get the soil test done early.

The steel brackets normally bolt down onto the finished slab. Cast in brackets are the exception, only where the loads demand them, and they are flagged at design stage so your concreter knows before the pour.

Always build the slab to the engineer's signed drawings.

Sources

Brian Best, founder and builder, Shed Homes

General information only. Rules change, so check the current rule with your state regulator or council. Shed Homes supplies home kits and engineered documentation, and does not build.